# Roadmap Execution Status Report
## Scope
This round continues executing the remaining in-plan work from `2026-04-17-scene-skill-60-to-90-roadmap-plan.md`.
It does not create new family contracts. It records the current roadmap execution state after `G1-E`, `G2`, and `G3` were all promoted into the same family-asset shape.
## Delivered
Added:
1. `tests/fixtures/generated_scene/roadmap_execution_status_2026-04-18.json`
2. `tests/roadmap_execution_status_test.rs`
## Current Plan Position
The roadmap is now recorded as:
1. `Phase 0 = completed`
2. `Phase 1 = completed`
3. `Phase 2 = completed`
4. `Phase 3 = completed`
5. `Phase 4 = in_progress`
Within `Phase 4`, the current track status is:
1. `Track A / G2 = batch-expansion-promoted`
2. `Track B / G1-E = batch-expansion-promoted`
3. `Track C / G3 = batch-expansion-promoted`
4. `Track D = in_progress`
5. `Track E = status-overlay-established`
## Why This Asset Exists
At this point, the repo already has:
1. family policy assets
2. family result assets
3. frozen ledger snapshot assets
4. current ledger overlay assets
5. family candidate-batch assets for all mainline families
The roadmap still needed one status asset that states, in one place, where the plan currently stands and what remains queued or deferred.
## Validation
Passed:
1. `cargo test --test roadmap_execution_status_test -- --nocapture`
2. `cargo test --test scene_ledger_status_test -- --nocapture`
3. `cargo test --test scene_generator_family_policy_test -- --nocapture`
## Outcome
The roadmap now has a repo-local execution-status asset that makes the remaining in-plan work explicit:
1. continue from queued mainline candidates
2. keep Track E overlays synchronized
3. do not reopen already completed P0 and family-baseline work